130367 - Establishment of Khyber Pakhtunkhwa University of Technology at Nowshera (Phase-I (KP)

130367 - Establishment of Khyber Pakhtunkhwa University of Technology at Nowshera (Phase-I

Approved cost of the Project : 2799.676

Project Start Date : 27/02/2019

Project End Date : 30/06/2022

Project Area : KP

SUB-SECTOR: Industries Department

Updated progress:

 

  • Progressive Exp: 1796.44
  • CFY Allocation: 700
  • CFY Release : 700
  • CFY Expenditure: 700


1. Status of Revised PC-I. Pre-PDWP held on 6.12.2021. Revenue Concurrence meeting of Finance Department will be convened shortly.
2. land acquisition stage. Payment of Rs. 158.6 Million made to DC, Nowshera for acquisition of land. Possession is still awaited.
3. Procurement details. Labs equipment and other items amounting Rs. 80 Million has been procured recently. Further procurements shall also be initiated after opening of Assan Assignment Account in NBP.
4. Hirirng of staff. Hiring of regular staff/faculty is in process.
5. Opening of Assignment account and subsequent transfer of released budget. Forms and other supportings are submitted to NBP Nowshera for opening of Assan Assignment Account.