Establishment of Bannu Economic Zone
Approved cost of the Project : 2,576.60
Project Start Date : 21/11/2024
Project End Date : 31/12/2025
Project Area : MA
- Expenses till 30th June 2021:48
- Expenses 2021-22 : 55.337
- Total Physical/ Financial Progress : 2.1
Remarks/Issues
- The 408 Acre land is Acquired.
- Construction of Estate Office is 100% completed.
- Business Plan is Approved by BOD KPEZDMC.
- Notice Inviting Tender published for contractor hiring on 2/3/2022 for Phase-I.
- Bid opening date is 16/3/2022.
- Contractor will commence the work in April 2022.
- Proposed inauguration date 22/3/2022.