Approved cost of the Project : 105.616
Project Start Date
: 18/09/2021
Project End Date
: 30/12/2024
Project Area : KP
SUB-SECTOR: SIDB
Updated progress:
- Progressive Exp: 105.615
- CFY Allocation: 0.001
- CFY Release : 0.001
- CFY Expenditure: 0
- PC-I for land acquisition submitted and is under consideration at P&DD.
- The cost assessment provided are not in accordance to Section-IV.
- The DC has been requested for Addendum/Corrigendum in the Section-IV and requested for re-assessment of the superstructure.
- On request of SIDB, the District Administration provided revised cost assessment on 24-12-21.
- Based on revised cost estimates, the Revised PC-I will be submitted shortly
- The Locals are resisting the land acquisition process.