190242 - Reconstructions of Government College of Technology (GCT) at Abottabad
Approved cost of the Project : 714.045
Project Start Date : 21/09/2020
Project End Date : 30/06/2023
Project Area : KP
SUB-SECTOR: TEVTA
Updated progress:
- Progressive Exp: 156.649
- CFY Allocation: 106.649
- CFY Release : 106.649
- CFY Expenditure: 106.649
1. What about expenditure against the parked funds in previous years. (Rs 10 Million utilized. Contractor has submit IPC of Rs 45 Million. Paymne tof balance fund is in progress)
2. Why is Zero expenditure in CFY (Fund transferred to TEVTA)
3. What about TS ??? (TS accorded)