210208 – Development of Infrastructure, Chitral Economic Zone
Approved cost of the Project : 463.026
Project Start Date : 01/09/2021
Project End Date : 31/03/2023
Project Area : KP
Updated progress:
- Progressive Exp: 10
- CFY Allocation: 10
- CFY Release : 10
- CFY Expenditure: 10
- Topographic survey has been completed.
- Master Planning and detail engineering design has been completed.
- Business Plan/ADP has been approved.
- 73/264 Kanal sealable area has been allotted.
- Construction work on the site has already been initiated.